Blackstone completed a Major Overhaul of a GE SNC 1-3 steam turbine. This included working with 2 technical representatives as part of a larger outage in which Blackstone had over 80 people on site including QA/QC, Safety and Project Management.
Remove split line bolting and upper casing (stone and inspect casing)
Remove and inspect linkage, and valve components
Remove HP carrier and nozzle block
Remove steam chest and carrier
Remove bearing housings and inspect bearings
Measure and record critical measurements (seal clearances, running position, hub measurements, bearing fits, nozzle block fit)
Install new rotor and record critical measurements: Journals; Rotor Mapping (axial clearances from stationary to rotating elements and radial clearances).
Reinstall removed components (nozzle block, seal carriers, seals, bearings) and record “as left” measurements
Complete “as left” alignment and monitor pipe strain
Disassembled (Rotor Out)
Disassembled (Rotor Installed)
Beneficios para el cliente
Tranquilidad de saber que su turbina funcionaría sin problemas hasta la próxima revisión de mantenimiento
El cliente recibió un Informe Técnico completo que detalla todas las mediciones de “cómo se encontró” y “cómo se dejó”, así como el estado de la turbina.