Blackstone completed a Major Overhaul of a GE SNC 1-3 steam turbine. This included working with 2 technical representatives as part of a larger outage in which Blackstone had over 80 people on site including QA/QC, Safety and Project Management.
Remove split line bolting and upper casing (stone and inspect casing)
Remove and inspect linkage, and valve components
Remove HP carrier and nozzle block
Remove steam chest and carrier
Remove bearing housings and inspect bearings
Measure and record critical measurements (seal clearances, running position, hub measurements, bearing fits, nozzle block fit)
Install new rotor and record critical measurements: Journals; Rotor Mapping (axial clearances from stationary to rotating elements and radial clearances).
Reinstall removed components (nozzle block, seal carriers, seals, bearings) and record “as left” measurements